Who can test for asbestos in Colorado
Only a Colorado-certified Building Inspector may run an asbestos inspection (Regulation No. 8, Part B, III.A.1.a), and CDPHE says that inspector works for a registered asbestos consulting firm. The inspector has to be independent of the contractor that will remove the asbestos (III.A.1.e). Cyclone Kleen Up is a CDPHE-certified asbestos abatement contractor (No. 26153), not a consulting firm, so we never sample a job we will abate. Cyclone can arrange the independent inspector for you, or you can hire your own.
What happens during an inspection
The inspector walks the building and sorts materials into "homogeneous areas" (one material that looks and was put in the same way). They touch each suspect material to see whether it crumbles by hand, which Colorado calls friable. Then they either treat an area as asbestos or take samples. The minimums are (III.A.3):
- Surfacing material, like popcorn texture: at least 3 samples for an area up to 1,000 square feet, 5 up to 5,000, and 7 above that.
- Pipe and boiler insulation: at least 3.
- Everything else, like floor tile or mastic: at least 2.
Texture or paint on drywall is sampled apart from the drywall under it (III.A.4.c), so you learn about both layers. If even one sample comes back positive, the whole area counts as asbestos (III.A.4.e).
How the lab reads your samples
The lab must hold NIST's NVLAP accreditation and be registered with CDPHE. It reads bulk samples under a microscope using EPA method 600/R-93/116 (III.A.4.a and III.A.4.b). A material with more than 1% asbestos is asbestos-containing material (I.B.16). If a friable sample is estimated at 1% or less but more than zero, the lab must recount it by a more exact method called point counting, or the material is treated as asbestos (III.A.4.d).
CDPHE's lab list shows 74 registered labs, 27 of them in Colorado. One in Colorado Springs reads bulk samples.
How long results take
It depends on the lab and the speed you pay for. One national lab lists turnaround options from same day to two weeks, with faster results costing more. Ask the inspector for their current turnaround before you set a start date for your remodel.
Testing before removal, and again after it
The inspection finds asbestos before work starts. After removal, a separate step called clearance checks the work area. Colorado requires a certified Air Monitoring Specialist, independent of the removal contractor, to do the final visual check and the clearance air test (Regulation No. 8, Part B, III.P). See our asbestos abatement page for how a removal job runs from start to clearance.
Buildings built after October 12, 1988
If the building, or the part being worked on, was built after October 12, 1988, the inspection can be skipped. The architect or project engineer who built it, or a certified inspector, signs CDPHE's form saying no asbestos was used (III.A.1.d). The rule itself adds that CDPHE "recommends that all buildings be inspected prior to any renovation or demolition activities, regardless of the date of construction."